Skip to content
- Call Before You Dig! Prior to any excavation work, call the national "Call Before You Dig" locating service by dialing 811, or (800) 424-5555, or online at Call Before You Dig to determine the location of existing underground utilities.
- If there are any existing easements on your property, provide a copy to Clallam PUD.
- Please review our Facility Access Policy (PDF) when deciding where PUD equipment will be placed on your property. The PUD must be able to access all meters, poles, transformers, and all other PUD-owned equipment with no delay or interference at all times.
- Costs will update annually from the estimate payment date and projects will be subject to a 36 month time limit for completion. This will affect all existing paid estimates.
- For information on Electric Line Guidelines, Electric Service Regulations & Requirements, Rates, or Deposits & Charges, visit our Electric page.
- Trenching and backfilling required for installation of underground cable is not included in your estimate and shall be provided by the customer. A PUD Serviceman will inspect the open ditch after cable install and before backfill.
- Contact your PUD Serviceman for a ditch inspection and wire installation before backfilling the ditch.
- If your project requires work within the County right-of-way, it will be your responsibility to obtain the necessary permit from Clallam County for all excavation performed within the County road right-of-way.
- Material availability; the District maintains a relatively large inventory of construction materials. However, some materials may not be available in District stock and may have to be ordered.
- Construction cost sharing; new line extensions are no longer eligible to receive sharing refunds from subsequent customers. New customers may be required to pay sharing refunds in accordance with existing sharing agreements. The terms of Construction Cost Sharing shall be defined in the most current revision of the Electric Service Regulations.