Construction Standards & Material Specifications
Electric Service Regulations
Annual Load Factor
The quotient of the annual electric usage divided by the product of the highest monthly peak demand multiplied by 8,760.
Approved Lessee
A person or legal entity furnishing evidence of a lease of sufficient duration and provisions, in the opinion of the General Manager of the District, to justify application of the Line Extension Policy for line construction to serve a proposed facility.
Billing Period
The normal billing period will be from 27 to 33 days and adjusted so that there are 12 billing periods per calendar year. The District reserves the right to adjust billing periods in order to facilitate operations.
General Service
Commercial and individual customers including schools, public agencies and other users not eligible under other rate schedules, further classified by demand as small, medium and large.
Contracted Service Location
The designated site on a parcel of land where service is requested by the person(s) initiating line construction, which site determines both timing and ownership of refunds which become available. To qualify as a Contracted Service Location, a site must be of adequate size to accommodate the facility stipulated in the Customer's contract.
Contribution in Aid of Construction
The construction cost of a line extension as paid by the Customer for lines installed by the District or installed by the customer under a modified Line Extension Agreement.
Conventional Subdivision
A subdivision of land such that installation of electric utility lines is required by the County for approval for marketing of building sites.
Customer
A person, commercial business, or other entity that has, or has applied for, a service account with the District.
Customer Funds
Any payments received for estimates issued by the District, such as advances on construction, conversions, relocations, sharing payments, or services listed in the Schedule of Deposits and Charges.
Developer
A person, commercial business, or legal entity requesting service to two or more dwelling sites, to a manufactured home rental facility, or to a multi-family structure.
District
Public Utility District No. 1 of Clallam County, Washington.
Financial Institutions
Banks, credit unions, and savings and loans.
Home Enterprise and Home-Based Industry Service
Home-based enterprise, business, or industries shall be defined by requirements set forth in the Clallam County Zoning Code under Zoning Code (CCC 33). When meeting these requirements, the service shall be classified as a Residential Service.
Idle Facilities
Overhead and underground lines and equipment which were installed as a means of providing service to customers and have not been used by the customer for active service for a period of one year or more.
Large Industrial Service
Customers with metered loads exceeding 1000kW subject to conditions described in the most current version of the District’s Electric System Rate Schedules.
Low Income
Meeting the guidelines established by state or federal regulations and administered by Community Action Council.
Manager
The General Manager of Public Utility District No. 1 of Clallam County, Washington, or authorized agent thereof.
Manufactured Home
A structure for residential occupancy (eating, sleeping, and sanitation accommodations) that is built on a permanent chassis designed to be transportable and is a minimum of 8 feet wide and 40 feet long excluding the tongue. (Formerly referred to as "mobile home.")
Nonconventional Subdivision
Any other subdivision of land, including short platting, where installation of electric utility lines is not required under County regulations.
Person
Human Beings, associations, co partnerships, and corporations, whether acting by themselves or by a servant, agent, or employee.
Residential Service
Applies to residential and farm customers for domestic, seasonal or recreational use. A residential service is service to any building, facility or structure that is associated with a residence, either single or multi family. For a farm to qualify for this schedule, it must include a residence.
Substation Capacity
Based on the most recent PUD planning study, the amount of available MVA divided by the rated MVA of the transformer during peak loading conditions.
Trench
Trenching, bedding, backfilling, compaction, restoration, and maintenance of subsequent ditch settling.
A. Contracts, Rates, and Resale
Electric service shall be provided upon accepted application; such application being a contract for service, subject to the Electric Service Regulations of the District. Rates shall be as detailed in the applicable Rate Schedule. Where, by special consideration of the Manager, more than one Customer receives service from one metering point, the basic charges may be multiplied by the number of Customers. Unless otherwise provided in the contract, the Customer shall not resell the electric energy provided under this Regulation. Any customer desiring to resell electric energy received under the terms of this contract shall be required to enter into a Submetering Service Provider Contract with the District.
- Effective Date of Contracts - All service contracts shall take effect from the day they are signed, and rates will be charged and bills rendered from the date the premises are connected with electrical power.
- Term of Contracts - All service contracts shall be binding and, unless otherwise specified, shall continue in effect until after notice of discontinuance is filed in the office of the District.
- Customer's Protection - No inspector, agent, or employee of the District may ask, demand, receive, or accept any personal compensation for any service rendered to Customers of electric power, or other persons, in connection with supplying or furnishing electric power by the District.
- Obligations of District to be in Writing - No promise, agreement, or representation of any employee or agent of the District with reference to the furnishing of electric power shall be binding on the District unless the same shall be in writing, signed by the Manager in accordance with the provisions in these Regulations.
- Liability for Violating Provisions of these Regulations - Any person violating any of the provisions of these Regulations shall be prosecuted in accordance with applicable laws; and in addition, the service of any person found guilty of violating the provisions of these Regulations may be disconnected, and the person violating shall be liable for all damage and expenses incurred by the District and for all electric power used by reason of such violation.
- Requirement to Meet Building Code Standards - No building shall qualify for service connection if it does not meet or exceed any Regional, State, County, Municipal, or District building code or energy-efficiency standard
B. Service Not Covered in Rate Schedules
Service may be supplied to Customers not coming within the scope of the regular Rate Schedules of the District; provided that such service shall be covered by separate contract, which may be subject to provisions of the District's power purchase agreements, and shall be approved by the Commissioners of the District. Examples include:
- New Service(s) involving line extensions in excess of 5,000 feet where estimated line operation, maintenance or capital replacement costs cannot be supported by estimated revenue within the applicable established rate schedule(s).
- New Service(s) that are primary metered.
- New Service(s) subject to non-standard regulatory or legal requirements and conditions.
C. Delivery Point
A delivery point will be established by the District for each customer.
D. Tax Adjustment
The amount of the total of any or all revenue, kilowatt hours, or other form of tax imposed by any municipal, federal, or state taxing body upon the District, may be apportioned by the Commission of the District according to the territory in which such tax or taxes may be effective and amongst the various different classes of service furnished therein, and shall constitute an additional charge to any amounts which may be billed to any Customer under any rate schedule or special contract covered by these Regulations.
E. Discontinuance of Service
The District reserves the right to cut off the supply of electric power and discontinue service in the event the Customer:
- Shall fail to comply with the District's Electric Service Regulations, Facility Access Policy or provisions of the Service Contract, or,
- After due-process, non-payment of a District invoice. Service may be disconnected by the District at any time to prevent fraudulent use or to protect its property. Reconnection will occur after satisfactory remedy to the District (see Section 8).
F. Board of Commissioners
The Board of Commissioners of Clallam County PUD establishes policies for the District. Any customer who wishes to comment on, make a recommendation regarding a policy, or who disagrees with a decision made by District staff may address the Commissioners at a regularly scheduled Board meeting.
G. Applicability of Electrical Service Requirements/Facility Access Policy
In addition to these Regulations, the District’s Electric Service Requirements and Facility Access Policy are also applicable to the installation, operation and maintenance of all District electrical facilities.
H. Right to Refuse Service
The District reserves the right to refuse to connect, or render service to, any applicant or any Customer where such connection and/or where the applicant or Customer has not complied with State, Municipal, or with this District Electric Service Requirements or Facility Access Policy concerning the rendition of service or has an unpaid obligation to the District.
I. Right to Enter Upon Premises
The District shall have the right, through its agents or employees, to safely enter the property of the Customer at all times for the purpose of: reading, inspecting, repairing, or removing metering devices, appliances, and wiring of the District; trimming or removing trees and brush around meters, transformers, or other equipment that may interfere with the safe and efficient operation of the utility system; maintenance of utility lines, both overhead and underground; and inspection, replacement, installation and removal of District facilities.
A. General Provisions
- Location - Permanent line extensions will normally be built in the most direct route from the nearest source of supply. However, availability of easements and maintenance considerations may affect line routing. Placement of line extensions shall be at the discretion of the Manager of the District.
- Trenches - The Customer or Developer shall provide trenches to District specifications for all underground installations.
- Easements - The Customer or Developer shall provide easements as required for the extension, in the location and of the width specified by the District.
- Ownership of Facilities - Ownership of any and all facilities constructed under the District's Line Extension Regulations shall remain with the Public Utility District No. 1 of Clallam County, Washington. Ownership of Customer or Contractor installed extensions will begin when approved and energized by the District.
- Increase, Maintenance, and Upgrading of Facilities - Any costs incurred to provide any increase in facilities beyond those requested or needed to serve the load of an individual Customer or Developer shall be absorbed by the District, provided that the Manager of the District shall be the final authority as to the size of facilities to be installed, and provided that certain standard and minimum facilities may be established as customary for District installation. Maintenance and upgrading of facilities for District purposes following initial construction shall be the responsibility of the District.
- Construction Cost Sharing
- Customers with paid construction estimates prior to September 19, 2022, shall be allowed sharing under April 11, 2022 Electric Service Regulations Resolution 2239- 22.
- Customers with paid construction estimates on or after September 19, 2022 may be required to contribute construction cost sharing to those customers eligible under April 11, 2022 Electric Service Regulations Resolution 2239-22.
- Construction and Ownership of Extension - The Customer(s) shall bear the entire cost of the extension and may elect either to have the extension constructed by the District in compliance with this Section or by a contractor of choice, in accordance with all specifications of, and subject to inspection (the cost of such inspection, etc. shall be paid for by the Customer or Customers) and approval by the District. Upon completion of the contractor extension, title thereto, together with all necessary franchises, easements, rights of way, and/or permits pertaining to the extension shall be conveyed to the District, and the District agrees to assume obligations and liabilities for maintenance and operation. In the event that the extension is built by a contractor:
- The extension shall be guaranteed by the Customer, for a period of not less than one year, against physical defects. Electrical service will not be made available until all requirements are met by the Customer(s).
- Proposal Cost - The District will provide line extension cost estimates to the Customer or potential developers. If the cost of preparing the estimate(s) exceeds $1,000, the customer or developer will pay in advance the estimated engineering cost for amounts in excess of $1,000.
- Unit Costs - The District Manager will establish unit costs (based on actual District cost) for components of the electrical system used in line extensions. These costs will be changed as needed to reflect current actual expenses.
- Cost Accounting - The District will review the actual cost of each line extension. If the actual cost exceeds the estimate by more than $200, the Customer will be invoiced for that amount in excess of the estimate; or if the estimate exceeds the actual cost by more than $200, a refund of the excess will be made to the Customer.
- Substation Capacity Charge - When an existing substation transformer will exceed 80% of full air-cooled transformer rating due to a peak load addition of more than 600 KVA, the requesting customer will be assessed a substation capacity charge. This charge will be based on the current estimated substation upgrade cost, and the existing transformer capacity shall be based on the most recent District planning study. Peak load addition will be based on 80% of the customer-submitted main disconnect panel amp rating. Primary metered services peak load addition will be based on PUD engineering calculation incorporating the following formula:Capacity Charge = A*B/(C-D) where:
- A = Current estimated substation upgrade cost
- B = Portion of load addition above 80% of existing transformer rating
- C = New transformer full air-cooled rating
- D = Current load on existing transformer
- Developer Substation Capacity Charge - When the load on an existing substation transformer is projected to exceed 80% of its full air-cooled capacity due to the addition of more than 600 KVA from a single development plat, the customer will be assessed a substation capacity charge. If the development will be built in phases, the developer substation capacity charge will be paid in the amount due per phase of the project. This charge will be determined by the current estimated cost of upgrading the substation, and will consider the existing transformer capacity as determined by the most recent District planning study. The projected increase in peak load will be calculated using the coincident peak load for all dwelling units listed on the development plat. Coincident peak load per dwelling unit will be computed using the most recent planning study engineering analysis for dwelling unit type, and quantity. Capacity Charge = (C*D)/(E-F) where:
- L = Load addition is calculated by multiplying the number of dwelling unit additions by the dwelling unit coincident peak load
- C = Current estimated substation upgrade cost
- D = Portion of “L” above 80% of existing transformer rating
- E = New transformer full air-cooled rating
- F = Current load on existing transformer
B. Residential Line Extensions
- New Service Charge(s) - The District's New Service Charge(s) shall be paid prior to connection to District facilities, and shall provide for installation of a transformer, overhead service conductor installation, underground service inspection and connection, and the District's portion of the metering equipment for a service to a single-family residence. In addition, a service pole may be installed, without cost to the Customer, if that service pole is required for the convenience of the District.
- Construction Costs - Where facilities construction is required to make service available to a single-family residence, the costs to the Customer(s) shall be determined as follows:
- The estimated cost of the facilities to be constructed by the District plus the New Service Charge will be determined by the District.
- The Customer(s) desiring service shall pay to the District the estimated cost of the facilities plus the New Service Charge.
C. General Power Line Extensions (Non-Residential)
- New Service Charge(s) - The New Service Charge(s) shall be paid prior to connection to District facilities.
- For General Power Accounts with Anticipated Annual Load Factors Equal to or Greater than 40 Percent. The District's New Service Charge(s) shall provide for installation of transformers, overhead service conductors, underground service connection and the District's portion of metering equipment.
- For General Power Accounts with Anticipated Annual Load Factors Less than 40 Percent. At the discretion of the Manager, some portion of the transformation and metering cost shall be paid by the Customer. Surcharges collected for transformation or metering shall not be sharable.
- For Primary Metering - The cost of primary metering shall be paid by the Customer, unless such primary metering is required by the District for its benefit.
- For a Service Pole - A service pole may be installed without cost to a General Power Customer if such service pole is required for the District's convenience.
- Construction Costs - Where facilities construction is required to make service available to a General Power account, the costs to the Customer shall be determined as follows:
- The estimated cost of the facilities to be constructed by the District plus the New Service Charge(s) will be determined by the District.
- The General Power Customer(s) desiring service shall pay to the District the estimated cost of the facilities plus the New Service Charge(s).
- Construction Cost Sharing
- Customers with paid construction estimates prior to September 19, 2022 shall be allowed sharing under April, 11 2022 Electric Service Regulations Resolution 2239- 22.
- Customers with paid construction estimates on or after September 19, 2022 may be required to contribute construction cost sharing to those customers eligible under April 11, 2022 Electric Service Regulations Resolution 2239-22.
D. Large Industrial Power Line Extensions
Line extensions for industrial and large power accounts shall be made by individual arrangement.
E. Developer Line Extensions
- Construction Costs - A Developer requesting extension of electric lines in Conventional or Non-Conventional Subdivisions or to provide service for manufactured home rental facilities or multi family dwelling structures shall pay to the District the District's estimated cost of the required facilities prior to work being scheduled.
F. Irrigation Line Extensions
- Line extensions built to serve irrigation pumps and/or nonresidential farm installations exclusively shall be constructed at the Customer's expense.
- The District's New Service Charge(s) shall provide installation of a transformer(s), overhead service conductors, and the District's portion of the metering equipment for the irrigation service. New Service Charge(s) shall be paid prior to connection to District facilities.
- Irrigation line construction costs shall be shared by additional Customers using the line, in the same manner as residential/commercial line construction costs.
G. Facilities
Line extensions will be owned and maintained by the District as long as customers utilize them for electric service. When it is determined that District facilities have been idle for a period of one year, the District has the right to remove the facilities or parts thereof. The District will attempt to contact the property owner to determine if he/she has a future need for the idle facilities. Customers who are not using any energy but wish to have the facilities available can do so by paying a monthly service charge as determined by the District.
A. Interruption of Service
The District shall exercise diligence and care to furnish and deliver a continuous supply of electric power to the Customer, but will not be liable for interruption or shortage of supply due to accident or conditions beyond the District's control. In the event of such interruption or shortage, the District shall not be liable for any loss or damage occasioned thereby, nor shall such interruption or shortage constitute a breach of its contract.
B. Claims for Damages
The District has a procedure to evaluate claims for damages. A Claim for Damages form will be provided to parties, at their request, who have experienced property damage as a result of District action or as a consequence of connection to District facilities. Provision of a claim form is not an admission of liability. The District will investigate each claim for damages and respond to the claimant.
A. Increased Use
- In order to prevent damage to the District's equipment and impairment of its service, the Customer shall give the District notice before making any additions to his connected load so that the District, at its option, may provide such facilities as may be necessary for the furnishing of increased service. Such additions include, but are not limited to, electric heating. The District reserves the right to limit service to any Customer.
- When increased load requires underground service conductor must be changed, the Customer must pay the expense of the installation of the new conductor and conduit, and the District will provide reconnection to its facilities.
- In cases where a Customer load increases enough at one time to require upgrading of District electrical facilities, the Customer will pay the charge set forth in the Schedule of Deposits and Charges. In cases where system upgrade to primary distribution, transmission, or substation is required, the Customer will pay the upgrade cost (subject to Section 3). (Exception: where the District determines that service conductor must be replaced with primary conductor to maintain adequate voltage for the original service panel size, the District will perform the work at no charge.) Where gradually increasing loads from multiple Customers requires upgrading of District electrical facilities, the upgrade will be at no charge to the Customers.
B. Balancing of Load
The Customer or contractor shall connect any equipment to keep the load, under normal operating conditions, balanced within plus or minus 10 percent of the average load across the phase wires.
C. Claims for Damages
If a customer believes that District action or connection to District facilities may have resulted in property damage, the customer should notify the District as soon as possible. The expense of contractor repairs and/or parts may not be reimbursed unless the District has first been contacted and had opportunity to respond to the situation. The District's Claim for Damages form is available for use by the Customer and will be helpful in making certain all pertinent information is provided.
D. Access to District Facilities
The Customer shall not permit access to District equipment or lines by anyone other than authorized representatives of the District. The Customer shall obtain and grant all necessary permission to enable District Representatives to install, maintain, service, or remove its facilities located on the Customer’s property.
A. Availability of Service
- Customer Requests Service - A Customer, before proceeding with the wiring or installation of equipment, shall request a determination of the availability of service from the District.
- Available Electric Service - The District will advise the Customer of the most suitable phase and voltage available on established circuits. Service will be installed, connected, supplied, and maintained in accordance with the District's Electric Service Requirements and these Electric Service Regulations.
- Protective Devices - Suitable protective devices on the Customer's premises may be required whenever the District deems such installation necessary to protect its property or that of its other Customers.
B. Temporary Service
- Availability - Temporary service will be supplied under applicable rate schedules and in accordance with the following conditions:
- The Customer will pay in advance the estimated cost of furnishing and removing the required facilities, less the value of materials returned to stock; provided, that where service conductors and a meter are required; the advance payment will be as set forth in the applicable Schedule of Deposits and Charges.
- The Customer will pay for such service at the monthly rate applicable to the class of service.
- Temporary service will be provided for one year from the date the service is connected to District facilities. The Customer may request continuance of temporary service annually thereafter, and the District may continue such service at the Manager's discretion. If continuance of temporary service is not determined to be safe, the Customer will be notified of termination of such service and will be given a reasonable time, not to exceed one year, to convert to a permanent service.
C. Service Installation and Maintenance
- Electric Service Requirements - The District's Electric Service Requirements are applicable to every service in addition to the subsections below.
- Overhead Services - Overhead service conductors will be installed by the District and attached to a connection point, acceptable to the District, provided by the Customer on the Customer's facility. In the case of metering on a District pole, the District will attach its conductors to the pole and connect to the Customer's wiring thereon.
- Service Poles - The District will furnish and install any service poles where they are required. Payment for service poles shall be as determined in Section 3.
- Underground Services - Underground service conductors will be provided and installed by the Customer or contractor, except that they will be connected by the District to District facilities. Residential underground service conductors must be installed to District specifications and inspected and approved by a District representative prior to backfill.
- Maintenance of Services
- The District will maintain the service conductors between the District’s transformer and the connections on the source side of the customer’s weather-head on all overhead residential, commercial and industrial services.
- Residential underground service conductors installed to District specifications between a District facility and the Customer's meter will be maintained by the District after acceptance and a one-year warranty period.
- Apartments and Condominiums - The underground service or services to any multi-unit residential structure or structures containing more than 4 individually metered dwelling units shall be classified as commercial with respect to the requirements of this section.
- Non-residential underground service installed from the District transformer to the customer’s point of metering will be maintained by the customer or the customer’s contractor at the customer’s expense. The District will assist, by request, in the maintenance by providing available resources at the customer’s expense.
- The Customer's point of metering of an instrument transformer installation is considered to be at the instrument transformer.
- Whenever a Customer requests changes to the service that affect the maintenance responsibility, the Customer will be so advised.
D. Service Entrance
- Location of Service Entrance - The applicant for service shall determine from the District the location of the service entrance and metering equipment. Any wiring installed without first determining service entrance and/or meter locations as covered above is done at the risk of having to relocate the service to conform with the requirements of the District.
- Number of Attachments - All service entrances will be so located that the service conductors installed by the District will reach the service entrance by attachment at only one location on the building.
- Specific Requirements - Specific requirements are contained in the District's Electric Service Requirements.
E. Customer Equipment on Poles
No equipment, devices, or wiring, other than service entrance equipment belonging to a Customer, shall be attached to District owned poles except by special permission from the District; and any such attachment shall be done strictly in accordance with District specifications.
F. Determination of Demand & Reactive
- Load Requirements - Demand metering shall be installed on services when demand or anticipated demand exceeds 50kW. Reactive metering shall be installed when the actual or anticipated power factor of the load is less than 98% lagging.
- Time Interval - Where the rate is based on kW demand, the kW demand shall be the highest 15-minute demand in the month, as determined by suitable indicating or recording instruments.
- Demands of Fluctuating Loads - For demands that are widely fluctuating, there shall be added to the 15-minute interval demand described in rate schedules an additional demand equal to 40% of the positive difference between the maximum one-minute demand minus 150% of the 15-minute interval demand.
G. Power Factor Adjustment
- Power Factor Charge - Under rate schedules providing for a kW demand charge, adjustment for power factor shall be made as detailed in the applicable Rate Schedules.
- Power Factor Correction - If the District determines that the power factor of a Customer's load is less than 95% lagging, the District may require the Customer to install proper equipment to prevent its power factor from falling below 98%.
H. Energy Efficiency
- Cities and County Areas - The current Washington State Energy Code and the current Washington State Ventilation and Indoor Air Quality Code are considered District-wide minimum energy efficiency standards for the applicable structures requiring code compliance.
- The District shall consider a certificate of completion or similar occupancy permit issued by a building official and recognized by the State of Washington or other official and/or agency approved by the District, as evidence of satisfactory compliance with the District's energy efficiency standards in lieu of verification by District representatives.
- Failure to secure the proper inspections and/or to comply with the District's energy efficiency standards will result in denial of service or disconnection.
- Federal and Tribal Areas - In those areas of the District's service territory not regulated by the State of Washington, the current Washington State Energy Code and the current Washington State Ventilation and Indoor Air Quality Code, as applicable to Group R occupancy, shall be considered the District's minimum energy efficiency standards. The standards shall be applied by the District in a way that parallels enforcement by the State of Washington for the purposes of regulating the distribution of electric energy in a uniform manner and providing for the actual and prospective needs of the District.
- District representatives shall be notified and allowed access to verify compliance with the District's energy efficiency standards.
- Failure to comply with the District's energy efficiency standards will result in assessment of an Energy Resources Surcharge in order to receive or maintain new or altered electrical service.
A. General
Approval of the District is required before installation of any single-phase motor exceeding 5 horsepower or combination of single or poly-phase motors exceeding 15 horsepower.
B. Large Motors
Starting of any motor shall not produce more than a 2% dip in primary voltage, or more than a 3% dip in service voltage of any other customer. Larger voltage dips shall be mitigated at the expense of the motor owning customer.
A. Deposits
- Residential - A deposit may be required from a residential Customer when applying for service and opening an account. An identity validation and credit assessment will be conducted for customers who are applying for service with Clallam County PUD. If a satisfactory credit rating is obtained through the assessment or you are an existing customer who has an established satisfactory credit rating with Clallam County PUD, you may be excluded from the deposit requirement. The deposit shall be as set forth in the District’s Schedule of Deposits and Charges.
- Nonresidential - A deposit may be required from a nonresidential Customer unless the Customer has established a satisfactory credit record with the District. The amount of such deposit will be determined by the District after consideration of estimated billings (see Schedule of Deposits and Charges).
- Additional or New Deposits - Nothing in these rules shall prevent the District from requiring additional or new deposits when conditions warrant.
- Refund of Deposits - At the discretion of the District, deposits may be refunded or credited to an account when the Customer, by prompt payment of all bills rendered over a period of 1 year or more, has established a satisfactory credit rating. Deposit refunds or credits will be as set forth in the District’s Credit Requirements, Customer Rights and Obligations policy. Deposits will be refunded upon termination of service after all outstanding amounts due the District have been paid.
B. Charges
Payment of charges, as set forth in the applicable Schedule of Deposits and Charges, will be required of all.
C. Payments
- Bills Payable Within 28 Days - All bills, for service rendered and minimum charges, are due when rendered and payable within 28 days from the statement billing date, unless otherwise specified, and if not so paid, become delinquent and subject to disconnection as outlined in Section 8.
- Delinquent Payments - When a Customer develops a history of delinquency with the District in that billings are not paid within a 28-day period as stipulated above, and further, are not paid for two or more occasions, which need not be consecutive, the District may, at its option, require a deposit or additional deposit as security.
- Budget Payment Plan - Budget Payment Plan shall be interpreted to mean that the Customer shall pay an estimated amount each month on or before the bill due date; and continuing on a regular monthly basis thereafter, and if not so paid, the amount may be deemed delinquent and subject to disconnection.
- At the option of the Customer Service Supervisor, new Customers of the District, including all Customers who have not established credit with the District, may be placed on a Budget Payment Plan at a monthly amount estimated by the Customer Service Supervisor. Such monthly payments are due on the date established, and if not so paid, shall result in the account associated with said payments becoming delinquent and being subject to disconnection.
- Right to Disconnect Service - The right to discontinue service for default may be exercised whenever and as often as default shall occur; and neither delay nor omission on the part of the District to enforce this rule at any 1 or more times shall be deemed a waiver of rights to enforce the same at any time, so long as the default continues.
- Notice of Pending Disconnection – Written notice will be sent to a customer by first class mail 5 days before service is discontinued under this regulation and will advise the Customer of the reason(s) for the disconnection action except in the case of fraudulent use of service, when the District may disconnect service without notice. For the purpose of this regulation, notice shall be considered to have been given when placed in the United States mail addressed to the Customer at his mailing address as shown on the District's records.
- Collection Notice - When it is necessary, in the opinion of the District, to mail a collection notice to any Customer (in addition to regular billing statement), a charge of the actual cost to the District may be added to the Customer's bill, in order that collection costs may be paid by those Customers creating said costs.
- Paid Estimate Updates - Increases to the cost of materials, labor, services and/or unit costs approved by the Board of Commissioners will be applied to any customer project that has not been completed within 12 months of the estimate payment date. Updated costs will be invoiced or refunded at the close of the project.
- Return of Customer Funds - Customer projects that are not completed within 36 months of the estimated payment date will be considered abandoned. The District will refund all remaining customer funds, prorated for any services already rendered by the District.
D. Returned Payment Charge
An accounting service charge (Returned Payment Charge), as set forth in applicable Schedule of Deposits and Charges, may be made to a Customer if a payment tendered to the District as payment for utility service is not honored by the Customer's financial institution because of insufficient funds, the bank account's having been closed, submission of incorrect financial information, or other irregularity. Payment of a delinquent balance with a dishonored payment submission may result in immediate termination of service.
Field Collection or Extension Charge A Field Collection or Extension Charge, as set forth in applicable Schedule of Deposits and Charges, may be made to a Customer who has not responded to a Disconnect Notice, requiring a District representative to make a personal visit that may allow for immediate electronic payment or arrangements for collection of the unpaid account.
E. Customer Rights
- Informal Conference - A Customer who disputes the amount of a bill when due, or who does not intend to pay the full amount of the bill or invoice when due, shall have the right to an informal conference with certain designated employees in the District.
- Informal conferences shall take place during the normal working hours 7 a.m. to 5 p.m., Monday through Thursday.
- The Customer may either appear in person in the District's office or confer by telephone.
- Such designated employees shall have the authority to reach agreements with the Customer for a deferred payment schedule of the particular bill.
- Appeal Hearings - If a Customer is not satisfied with the determination of the District's designated employee during the informal conference, the Customer may schedule a hearing with the District Hearing Officer.
- The Hearing Officer and any Deputy or Assistant Hearing Officers shall be management level employees and shall be appointed by the Commission from employees whose other duties are not connected with the credit section.
- A written or verbal appeal by a Customer must be filed with the Hearing Officer within 5 working days after the determination of the informal conference.
- In response to a timely appeal, the Hearing Officer shall arrange an appeal hearing at a mutually convenient and accessible location or conduct the hearing by telephone. Such hearing must be scheduled during normal working hours 7 a.m. to 5 p.m., Monday through Thursday, and within ten (10) days of receipt of the Customer's appeal.
- If the Customer requests, a record will be made of the proceedings. The Hearing Officer may use a recording device or other means of preserving a record which he/she deems appropriate; the Customer may provide, at his/her own expense, a court reporter, or supplemental means of providing a record. The Customer shall have the right to counsel.
- The Customer shall open the hearing with a statement of the nature of the appeal and shall present whatever evidence the Customer deems relevant. The Customer shall have the reasonable right to examine the records of the District relating to his/her account. After the Customer has completed presenting his/her appeal, the appropriate District personnel shall provide the District's position. The Customer shall have the right to rebuttal.
- The Hearing Officer shall provide the Customer with a written decision setting forth (a) the nature of the Customer's appeal; (b) the decision of the Hearing Officer; and (c) the reasons for the decision of the Hearing Officer. The written decision shall be promptly sent to the Customer by certified mail and may also be communicated by telephone.
- Service will not be disconnected while an appeal is pending provided that the Customer has complied with the above procedural requirements. The Customer shall have three days following the receipt of the written decision of the Hearing Officer to comply with the terms and conditions of the decision. If the Customer fails to take the action required by the Hearing Officer, including payment of a past due bill, or if he/she refuses to accept receipt of the Hearing Officer's decision, the District may disconnect service without further notice to the Customer.
F. Reconnection Charge
Whenever service has been discontinued as per these Regulations, a charge, as set forth in the District's Schedule of Deposits and Charges, will be made for restoring service. In the event that the actual cost of labor, transportation, and overhead to cover the expense of such restoration exceeds the designated charge, the Customer shall pay the actual cost.
G. Meter Testing
- When a Customer inquires into his/her billing for any particular month, the District will, upon request, have such meter reread and the service inspected for defects. Should the Customer then desire that the meter be tested, he/she shall be required to make a deposit, as set forth in the Schedule of Deposits and Charges, to cover the cost of making such test. The meter will then be tested.
- Should the meter show an error of over two (2) percent, said deposit will be refunded to the Customer, the meter corrected, and the bill adjusted. If the test of such meter should show an accurate measure within two (2) percent, the deposit will be retained by the District to cover the cost of testing. Whenever it shall be determined that any meter has not been registering correctly, then an average bill may be rendered, based either on the nearest four preceding months' average use when the meter was in good order, or on the same month of the preceding year if the use is seasonal.
H. Meter Tampering Charge
- Any Customer receiving unmeasured or unauthorized electrical services is responsible for paying the full amount of said services reasonably determined by the District to have been diverted around the meter or received unmetered or unauthorized due to meter tampering, alteration, or replacement.
- A Meter Tampering Charge, as set forth in Schedule of Deposits and Charges, will be added to the estimated billing for unmeasured or unauthorized services to cover the expense of District equipment restoration. In the event that the actual cost of labor, transportation, and overhead to cover the expense of such restoration exceeds the designated charge, the Customer shall pay the actual cost.
I. Meter Reading and Estimations
- Meters will normally be read and bills rendered on a monthly cycle, except for Irrigation Service and certain remote or contract accounts. Readings may be done electronically.
- If, in the opinion of the District, inclement weather or other extenuating circumstances make it impossible for the District to read meters for a temporary period, the District reserves the right to estimate meter readings and render bills based upon such estimates. Estimates will be based upon account history and weather factors. Actual energy consumption will be confirmed and adjusted as necessary with a subsequent regular meter reading cycle.
- Closing meter readings will be done on the business day requested by the Customer.
J. Billing
- Regular Bills - Bills for the regular billing period will be rendered based upon the meter reading or estimate.
- Closing Bills -Closing bills will normally be rendered within seven (7) days of the Customer requested disconnect date.
- Billing Error Adjustments
- The customer is financially responsible for all electric energy or water passing through their meter. In the event of a billing error, such as equipment failure or employee recording error, the District will make an adjustment to the billing on the basis of the best information available.
- In the event the adjustment is in favor of the customer (present or previous), the District will credit the customer’s account or refund the credit. The retroactive billing computation will be limited to the 36-month period measured immediately prior to the time of the correction.
- In the event the adjustment is in favor of the District, a retroactive bill to the customer will be provided. The retroactive billing computation will be limited to the 36-month period measured immediately prior to the time of the correction. The customer may choose to pay the retroactive bill over a period of time as agreed to with the District.
A. Validity
If any section, subsection, subdivision, sentence, clause, or phrase of these Regulations is for any reason held to be unconstitutional or void, such invalidity shall not thereby affect the validity of the remaining portions of these Regulations.
B. Effective Date
These Regulations are to take effect and be in force from the 22nd day of September, 2022.
C. Electric Service Regulations Revision Log
| Revision Date | Distribution Date | Intranet Upload Date | Comments |
|---|---|---|---|
| 12/13/2021 | 12/13/2021 | 12/13/2021 | Added language in Section 3A (General Provisions) |
| 4/11/2022 | 5/1/2022 | 5/1/2022 | Change cost accounting Section 13 |
| 8/29/2022 | 9/19/2022 | 9/19/2022 | Eliminate Sharing Regulations |
| 4/22/2024 | 5/1/2024 | 5/1/2024 | Added customer funds definition and policy for updating estimates and returning customer funds. |
Electric Service Requirements
Section 1.1 Application for Service – Contract
Electric service shall be provided upon written application, such application being a contract for service, subject to the Electric Service Regulations of the District. Rates shall be as detailed in the applicable Rate Schedule.
Section 1.2 Compliance With Codes
All Customer electrical equipment and wiring must be in accordance with the current edition of the National Electrical Code (NEC) at the time of installation.In addition, the Customer must comply with State, County, and Municipal Codes.
Section 1.2.1 Conflict Resolution
Any conflict between this policy and the NEC or other Codes shall be resolved by the Manager of the District.
Section 1.2.2 Variances
When conditions exist that renders the application of any particular requirementto be impracticable or impossible, a variance may be granted. A variance will not be granted that is justified only by economics. Variances to these Electrical Service Requirements can only be issued by the Engineering Manager, with the concurrence of the Operations Superintendent responsible for the area the variance occurs
Section 1.3 Inspection Approval Required
No new service connection will be made unless Contractor’s or Customer’s electrical work permit is attached to the service entrance or service switch and approved by the proper electrical inspection authority, in accordance with RCW 19.28.210. and District Policy
No increased, relocated or otherwise altered service will be reconnected unless Contractor’s or Customer’s electrical work permit is attached to the service entrance or service switch.
Section 1.4 Space and Protection Provision by Customer
The Customer shall provide sufficient space and exercise proper care to protect District property on his/her premises. In the event of loss or damage to District property on the Customer’s premises arising from neglect, carelessness, ormisuse, the cost of necessary repairs or replacement will be billed to the Customer.
Section 1.4.1 Safe Access to Facilities
The Customer shall keep the area around all meters, transformers, and other District facilities on the Customer’s property free of vegetation, health and safety hazards, debris, and obstructions, to ensure clear and safe access at all times
Section 1.5 Valid Address Required for Service
Before a meter can be installed, the Customer must obtain a valid service address from the proper agency. Apartment unit or space numbers are considered part of the valid address. Certain exceptions may be approved by a District representative. Examples are services to highway lighting, signs or irrigation pumps
Section 1.5.1 Clear Permanent Meter Marking
Each meter position and each service switch or breaker shall be clearly and permanently identified by the Customer to indicate the particular locations supplied by it. Meters will not be installed nor service energized until marking is complete
Examples of clear, permanent markings are:
- An identification plate attached by screws or rivets
- Commercially engraved tags with a raised relief surface
- Waterproof paint applied with stencil
Clear identification means an apartment/store space letter or number, or street address/number. The store name may be included, however, it does not constitute a clear designation in itself.
Section 1.5.2 Owner Responsibility for Marking Meters
It is the responsibility of the Owner or Manager of multi-unit complexes to notify the District of any changes in unit or apartment numbering so that the District’s personnel may verify metering circuits. Such notice must be given in writing to the District to permit re-designation of meters serving the premises. The Owner or Manager will be responsible for renumbering both the premises and meter sockets prior to dispatch of District personnel
The Owner or Manager shall be present when the building is initially energized to verify that the proper service is energized as the District’s connections are completed.
Section 1.6 Load Balance Within 10%
The Customer or his Contractor shall connect his equipment to keep the load, under normal operating conditions, balanced within plus or minus 10% of the average load across the phase wires.
Section 1.7 Customer Equipment on District Poles
No equipment, devices or wiring, other than service entrance equipment belonging to a customer, shall be attached to District-owned poles except by special permission from the District, and any such attachment shall be done strictly in accordance with District specifications.
Section 1.7.1 Meter Location & Rewiring
Meter locations required for new service or customer rewire work will conform to this policy even if other existing meters on the premise may not conform. Rewiring work shall include the upgrading of Customer metering equipment and requires that all new or modified equipment be installed and located in accordance with the requirements of these Electric Service Requirements. Rewiring work, as used in this section and other sections, does not apply to maintenance repairs and/or replacement of defective customer equipment with the same or similar equipment.
Section 1.7.2 Cost of Relocation
When any changes, alterations, or additions are made on the Customer’s premises that violate these requirements, the Customer shall pay the cost of relocating District facilities.
Section 1.7.3 Failure To Comply With Requirements & Access Policy
Failure to comply with the current District Electrical Service Requirements, Regulations or Facility Access Policy may result in refusal to connect a service or disconnection of an existing service.
Section 1.8 Energizing Service
Except where isolated by an open main service disconnect, the property owner or their representative shall be present at the time of connect or reconnect, or shall indicate in writing that their presence is not required and that all customer equipment is in a satisfactory state or condition to be energized. This requirement may be waived at the discretion of the District when reconnecting a service under the same active account and account holder within 96 hours of a disconnect.
Section 2.1 General
Section 2.1.1 Availability of Service
The availability of service for the equipment to be used shall be determined from the District before proceeding with the wiring or the installation of equipment.
Section 2.1.2 Phase & Voltage To Be Supplied
The District will advise the Customer of, and supply him with, the most suitable phase and voltage available upon established circuits. Three-phase, 3-wire services are not allowed by the District.
Section 2.1.3 Fault Current
The District will advise the Customer of available fault current either at the transformer or the metering point. It will be the Customer’s responsibility to provide service equipment rated for the available fault current. In no case shall Customer utilize “cable protectors” ahead of the meter to limit fault duty.
Section 2.1.4 Service Refusal
The District reserves the right to refuse to connect, or render service to, any applicant or any Customer where such connection and/or where the applicant or Customer has not complied with State, Municipal or District regulations concerning the rendition of service.
Section 2.1.5 Access to Premises for Maintenance
The District shall have the right, through its agents or employees, to safely enter the property of the Customer at all times for the purpose of reading, inspecting, repairing, or removing metering devices, appliances, and wiring of the District, trimming or removing trees and brush around meters, transformers, or other equipment that may interfere with the safe and efficient operation of the utility system, maintenance of utility lines, both overhead and underground, and inspection, replacement, installation and removal of District facilities.
Section 2.1.6 Protective Devices
Suitable protective devices on the Customer’s premises may be required whenever the District deems such installation necessary to protect its property or that of its other Customers. See Drawing #35 regarding guard posts for padmount equipment.
Section 2.1.7 Conductor Common Legs Marked
All service conductors provided by the Customer will be marked by the Customer or Contractor with colored tape to identify common legs of the service at the point of connection to District facilities. (See Drawings #21, 22, 23, 25, 26, 27 and 28).
Section 2.1.8 Overhead Service by District
Overhead service drops will be run by the District and attached to a connection point acceptable to the District, provided by the Customer, on the Customer’s facility. (See Drawings #1, 2, 3, & 4). The point of demarcation is the connections between the District service wire and the Customer’s service wire on self-contained metering and building mounted C.T. enclosures. In the case of metering on a District pole, the District will run the drop to the pole and connect to the Customer’s wiring thereon. The point of demarcation is the connections between the District service wire and the Customer’s service wire, near the weatherhead on selfcontained metering installations and at the current transformer(s) on pole top C.T. metered installations. (See drawings #7 and 8)
Section 2.1.9 Underground Service Cable in Conduit by Customer
The Customer will install underground service conductors in conduit, 2 inches minimum diameter between District facilities and the point of metering in accordance with specifications contained in these Requirements. Service conductors shall not be installed until a continuous conduit run has been installed from the metering point into the pad mount transformer or secondary enclosure and approved by a PUD Representative. Service conductors may be installed on services that are fed from a PUD pole if the first 10 feet of schedule 80 conduit has been attached to a standoff bracket on pole. (See Chart #2)
Section 2.2 Service Supply Conductors – Overhead
Section 2.2.1 District-Provided Service Poles
The District will furnish and install service poles where they are required. Payment for service poles shall be as determined in Section 3--Line Extension Regulations of the Electric Service Regulations.
Section 2.2.3 Attachment Vertical Clearance
Service drop clearances shall comply with appropriate requirements of the Washington Administrative Code (WAC), National Electrical Safety Code (NESC), and the NEC. Service drop conductors shall not be readily accessible to physical contact. Changes, additions, and/or grading on Customer premises shall not cause clearances under and around service wiresto be lessthan indicated herein. District shall be advised when clearance problems exist. In some cases, Customer may be responsible for costs incurred to restore clearances. Improper clearance is reason for disconnection of service. (See Drawings #4 and 5).
Section 2.2.4 Service Conductor Clearances Above a Roof
The point of service attachment on the building shall be such that both the attachment and the lowest point of the drip loop will be at least 10 feet above finish grade. The attachment must be high enough to allow 15' of conductor clearance over driveways, and the point of contact should be within 2 feet of the weatherhead. Where necessary, approved structures to support service conductors and for reinforcement of a building structure to provide adequate anchorage for service drop, conductors shall be provided by Contractor or Customer. (See Drawings #2, 4, and 5). Conductors shall have a vertical clearance as appropriate for pedestrian and vehicular traffic on roofs as shown on Drawings #4 and 5 herein.
Exception No. 1: Where the voltage between conductors does not exceed 300 and the roof has a slope of not less than 4 inches in 12 inches, a reduction in clearance to 3 feet shall be permitted.
Exception No. 2: Where the voltage between conductors does not exceed 300, a reduction in clearance above only the overhanging portion of the roof to not less than 18 inches shall be permitted if:
- Not more than 4 feet of service-drop conductors pass above the roof overhang, and
- They are terminated at a through-the-roof raceway or approved support.
Section 2.2.5 Service Conductor Clearance Above Ground
Service drop conductors, where not in excess of 600 V nominal, shall have minimum clearance from final grade as shown on Drawing #4.
Section 2.2.6 Service Conductor Clearances From Openings
Service conductors shall not be installed beneath openings through which materials may be moved, such as openings in farm and general power buildings. Overhead wires shall not be run such that they obstruct entrance to these building openings.
Section 2.2.7 Service Drop Attachment
The service entrance must be located where there is adequate material and strength for the District to attach its service drop. The attachment must have sufficient height to provide the required service drop and drip-loop clearances as specified herein. The attachment point must be accessible by ladder.
Preferred points of attachment are building studs or solid masonry at least 1 foot from a corner. Some trim and soffit boards are acceptable when substantially reinforced. Weatherhead attachments are acceptable provided adequate clearance from the roof is maintained.
Where a mast is over 26 inches tall or the service attached to it is over 100 feet long, the mast shall be guyed. (See Drawings #2 and 3 for details).
Section 2.2.8 Low Building Provision
When the building is too low to obtain proper clearance for the service wire attachment, Customer must provide an approved upright or service mast of rigid metal conduit of sufficient strength and height for the attachment of the service drop wires. Minimum acceptable mast shall be 2 inches galvanized steel conduit. (See Drawings #2 and 3).
Section 2.2.9 Multiple Service Entrance-Spacing
When more than one service entrance is provided on a building, the spacing between the service entrances should not exceed 24 inches without special permission. Consideration for exceptions would include:
- Fire pumps where separate service is required
- Emergency required standby
- Multiple occupancy buildings with limited space for service entrance
- Capacity requirements in excess of 2000 ampere per service
- Large Area Buildings
- Different electrical characteristics (phase, voltage, phase, etc.)
Section 2.2.10 Service Entrance Clearance From Adjoining Property
36 inches is required as the minimum permissible clearance between the front of metering equipment and/or meter and the adjacent property line.
Section 2.2.11 Rewiring Existing Service Entrance
The service entrance from an existing supply bus on a building may be changed or increased in capacity at its present location if it is in compliance with existing District Requirements.
Section 2.3 Underground Service Supplied by Customer
The Customer shall provide and install service cable and conduit in a trench also provided by the Customer. See Section 8 for trench requirements.
Section 2.3.1 Underground Service Cable “Tails” by Customer
Service cables shall be provided by the Customer in lengths adequate to extend up the pole to the secondary or the transformer terminals (including street crossings). (See Drawing #6). For padmount transformers or pedestal sources, sufficient tails shall be left to reach the appropriate connectors. (See Drawings #31, 32, and 33).
Section 2.3.2 Lateral Not Enclosed
Service entrance provided from underground distribution systems shall be located and terminated in accordance with District design standards. The service lateral shall not be enclosed within or covered by any alteration, facade, or addition to the building. The meter conduit risers may be located within footing, foundation and wall of the exterior wall of any building that is constructed with a flush-mounted meter base.
Section 2.3.3 Cables Rated for Service Environment
Cables to be installed in conduit or buried in direct contact with the earth shall be a type designated by the Washington State Department of Labor and Industries or NEC for the application (e.g. direct buried in dirt, in conduit, exposed to UV).
Section 2.3.4 District Standards for Cable Sizes and Types, Number of Runs and Conduit Sizes
See Section 11, Charts 1, 2 and 3.
Section 2.3.5 Cable Connection by District at District Facility
Underground service runs provided and installed by the Customer or Contractor will be connected by the District, to District provided facilities. For all conductor sizes larger than 350 MCM, the customer or the customer’s contractor will furnish the District with 2-hole NEMA spades, 1-¾ inches in width for each conductor to be terminated at the District’s transformer. (or as directed by District Rep)
Section 2.3.6 Cable Connection by Customer at Service
The Customer or Contractor will connect service cables at the point of metering.
Section 2.3.7 Maintenance of Underground Services
A) Residential Service Maintained by District
The District will maintain all underground residential services, installed to District specifications, up to the point of metering after a one-year warranty period. After the District accepts the installation, and after a one-year warranty period, the District will be responsible for the service up to, but not including, the meter base lugs on self-contained meter installations and at the current transformer on C.T metering installations.
Whenever a Customer requests changes to the service that affect the maintenance responsibility, the Customer will be so advised.
B) Apartments and Condominiums
The underground service or services to any multi-unit residential structure or structures containing more than 4 individually metered dwelling units, ownedand operated as a single general power entity, shall not be classified as residential with respect to the requirements of this section.
C) General Power and Industrial Services Maintained by Customer
All underground services to general power or industrial customers will be maintained by the customer or the customer’s contractor at the customer’s expense. The District will assist, by request, in the maintenance by providing available resources at the customer’s expense.
Section 2.3.8 Trench Inspection by District
Residential service conduit on the source side of metering must be inspected and approved by a District representative after installation in the trench, but prior to backfill. (See Drawings #30, 31, and 32 for details).
Section 2.3.9 Splices Not Allowed
Splices are not accepted on new residential cable installations on the source side of metering.
Section 2.3.10 Residential Service Cable Burial Depth
Underground residential service to the point of metering shall be installed at a depth of 42 inches. Where solid rock or obstructions prevent compliance with this depth requirement, reduction in depth and associated additional protective requirements shall be determined by a District representative. (See Drawing #30)
Section 2.3.11 Riser Conduits by Customer
All pole risers shall be installed on poles utilizing standoff brackets as indicated on Drawings #6, 7, and #8. The Customer or electrician shall attach only the first 10 foot section and the District will complete the installation. The Customer or electrician shall provide the remainder of the material and conductor to complete the installation as shown. If a conduit riser exists on a pole, the new riser must be installed using existing standoff brackets and mounted adjacent to the existing conduit.
Riser pole conduit shall be rigid galvanized metallic conduit or schedule 80 PVC for the lowest 10 foot section. Conduit above the lowest 10 foott section may be schedule 40 PVC. Nonmetallic conduit must be UV resistant.
Riser conduit on a building ahead of the meter base shall be rigid galvanized metallic or schedule 80 PVC. (See Drawing #11).
Section 2.3.12 No LB Fittings in Service Conduit
Conduit installations for cables shall not include conduit elbow fittings (LB). Standard conduit bends must be used. Bend radius should be 24 inches or larger. Conduit elbow fittings (LB) shall not be used ahead of metering. (See sweep specifications, Chart #1.)
Section 2.3.13 the Riser Bend
The Riser Bend shall be provided and installed by Customer between the continuous conduit and the pole riser. The bend shall be PVC Schedule 40 or Schedule 80, rigid non-metallic electrical conduit. The bend shall be installed at the time of conduit installation. The District will extend conduit up pole. The proper location of the Riser Bend on the pole (quadrant) shall be obtained from District representative. Where the Riser Bend is to be extended to a location requiring pole setting, replacement, or alteration by the District, such extension shall not bemade until the pole work is completed by the District.
Section 2.3.14 Conduits Into Existing Transformers
Conduit into existing transformers or secondary pedestals is to be installed by the District. The Customer or Contractor shall install conduits for new general power or industrial installations into the secondary area of the transformer site prior to the new transformer installation.
Section 2.3.15 Conduit Sealing for Below-Grade Locations
Termination of secondary distribution conduits within the building below grade is not a preferred installation due to water seepage problems. It has proven to be very difficult to insure long-term water tightness of the conduit and cables through the building wall. It is the Customer’s responsibility to provide drainage and sealing as needed to prevent damage to the electrical facilities and other property inside the building.
Section 3.1 General
Section 3.1.1 1 Main Meter for Service of Same Type
The District will furnish and install only one main watt-hour meter to register all energy of the same type of service supplied to Customer at any individual premises, unless accuracy of measurement, engineering, safety reasons, rates, or legal provisions require the installation of more than one meter except as provided for in Section 3.1.6 below. There may be Customer expense for additional requested meters.
Section 3.1.2 Customer Provides Meter Mounting Equipment
The Customer is required to purchase, install and maintain appropriate metermounting equipment in accordance with the requirements of the latest edition of these Requirements.
Section 3.1.3 Meter Mounting Equipment Defined
Meter-mounting equipment includes meter sockets, pedestal supports with concrete pad as required, current transformer cabinet, switchgear, landing pads, weatherhead, conductors, conduits, and supports as appropriate for the service. See Section 3.6 for additional details.
Section 3.1.4 Series Metering Not Allowed
Meter shall be located to directly measure Customer load. Series (subtractive) metering will not be allowed unless specifically approved by the District.
Section 3.1.5 Failure To Install Meter-Mounting Equipment
Failure to install meter-mounting equipment by Customer/Contractor meeting these requirements may lead to the delay of service until these requirements are met.
Section 3.1.6 Individual Meters Required
The District requires the installation of individual electric meters on all units in multi-occupancy residential and general power buildings and mobile home parks.
Section 3.1.7 Adding New Meters to Existing Service
New meters may be added to the existing service subject to the ampacity limitations of the service entrance conductors or service equipment. If the added loads served from the new meters require rewiring, then all (new and existing) meters shall be located in accordance with the District’s current meter location policy
Section 3.1.8 Demand Metering
Demand metering shall be installed on services in accordance with current District Rate Schedules and on all reactive metered accounts.
Section 3.1.9 Reactive Metering
Reactive metering shall also be installed on motor loads exceeding 50 horsepower or when the District determines the power factor of the load would be less than 95% lagging.
Section 3.1.10 Customer Monitoring
For customers who request to monitor and/or control energy use or demand, the District shall provide meter K, Y, and Z pulse signals as available via a District owned and operated optical isolator relay. Customer monitoring will be provided on a cost basis.
Section 3.1.11 Grounding of Metering Equipment
All metering equipment shall be bonded to ground rods installed at the location.
Section 3.2 Meter Locations
Section 3.2.1 General
In general, all electric meters must be located outdoors at the point closest to the service drop or lateral termination except as defined below. This policy applies to all new installations and rewire work where the meter and/or service equipment is involved. All meters shall be located and mounted in devices in accordance with the requirements of this manual, and acceptable to the District.
Meters shall not be enclosed or the installation modified in such a way so as to impede safe and convenient access to the meter and associated equipment. Nothing shall hinder or prevent the inspection, removal or installation of meters and other metering equipment, meter rings, meter seals or other locking devices.
Section 3.2.2 Location of District Facilities
The District shall determine the location of the remote metering pedestal, service entrance, service pole, or other metering equipment prior to installation. Customers who install wiring or equipment without an approved location from a District Representative shall be at risk of having to change the service location to conform to the requirements of the District. This requirement applies to all new installations and future modifications or repair work where the meter and/or service equipment is involved.
Section 3.2.3 Location Not at Rear of Residence
Residential meters may be located remotely or attached to the residence as shown on Drawing #12. Meters shall not be located at the rear of houses or buildings without pre-approval from a District Representative and safe and unrestricted access is provided at all times from an alley or street along the property line directly behind or on either side of the house or building. (See Electrical Requirements Drawing - #12)
Section 3.2.4 Meter on Outside Building Line
Installation of meters on buildings shall be on the outside lines of the building and shall be grouped in such a manner that a single service drop may serve all meters.
Section 3.2.5 Meters Shall Not Be Enclosed
Meters shall not be enclosed in garages, carports, breezeways, porches, or such locations where subsequent additions, rewiring, or remodeling could enclose the meter.
Section 3.2.6 Meters Shall Be Grouped
Individual meters associated with a single structure or facility shall be grouped at locations approved by the appropriate District representative. The number of meter centers in an apartment building shall not exceed 1 for 3 floors without District approval.
Section 3.2.7 Safe Meter Location Required
The Customer shall furnish a location to install the metering equipment that is acceptable to the District, not subject to excessive grade, and that will provide longterm, safe access to District employees, be free from vibration, corrosive atmosphere, abnormal temperatures, dust, water, etc.
Section 3.2.8 Meters Shall Be Readily Removable
All meters shall be readily removable (i.e.: not plastered in or built in). The surface of the meter base shall not be recessed behind the exterior wall surface. A meter installed in any alley or driveway must be flush mounted on the wall and protected adequately to prevent damage from vehicular traffic. See Drawing #2.
Section 3.2.12 Manufactured and Mobile Home Service Location
The National Electrical Code distinguishes between Mobile homes and Manufactured homes for the purpose of service equipment (NEC 550-32).
Section 3.3 Mounting Heights and Clearances
Section 3.3.1 Drawings
Meter mounting heights and clearances are shown on Drawings #7, 8, 10, 11, 13, 14, 15, 16, 17, 24, 25, 26 and 27.
Section 3.3.2 General
The Customer shall maintain clear access to and clearance in front of meters and metering equipment for District employees at all times for readings, testing, changing, removing, inspecting and servicing such equipment. The clear space in front of the meter equipment shall be a minimum of 36 inches deep, and as wide as the equipment or 36 inches, whichever is greater; and to a minimum height of 6 feet and 6 inches or the top of the equipment, if greater.
All meters shall be surface or flush mounted and not recessed. A minimum side and overhead clearance of 18 inches shall be maintained from the center of the meter opening, or any of the openings contained in a multiple meter socket.
Clearance, clear access, and working space shall be free of obstructions such as: piping, ventilating ducts, tanks, steps, rubbish, storage shelves, drums, pumps, air conditioning equipment, decks, chimneys, down spouts, building projections, and other equipment.
Section 3.3.3 Single Socket Meters
Except as otherwise stipulated by the District, individual meter sockets shall be mounted such that the center of the meter opening is between 5 feet and 0 inches and 6 feet and 0 inches above grade. (See drawings 4, 5, 7, 8 and 11)
Section 3.3.4 Single Meter Pedestals
Underground supplied individual meter pedestals shall be mounted such that the center of the meter opening is between 3 feet and 4 feet above grade. (See Drawings #14, 15, 16, and 17). Each meter pedestal shall be fed independently from District facilities.
Section 3.3.5 Multiple Meter Sockets
Multiple meter sockets shall be arranged so that the minimum vertical distance between meter openings is 10 inches and the minimum horizontal distance is 8 inches. Vertically grouped multiple meters shall be installed such that the top meter(s) are not more than 6 feet from the center of the meter opening to grade, nor the bottom meter(s) less than 3 feet from the center of the meter opening to grade. (See Drawing #24).
Section 3.3.6 C.T. Meters Mounting Height
Current transformer-rated test switches, phase shifting transformers, and recorders shall not be less than 36 inches above finished grade or floor immediately below the socket with the reference point at the bottom of the device in question
Section 3.3.7 Protect Meters From Hazards
Meter sockets and enclosures shall not be elevated to avoid hazards but must be protected from pedestrian and vehicular traffic or parking hazards by Customer. (See Drawing #35 regarding guard posts).
Section 3.3.8 Meters More Than 6′ Above Grade
If, as a result of an action of the Customer that causes the meter to become more than 6 feet above grade and in the opinion of the District it is feasible and preferable to lower the metering equipment to a location between 5 feet and 6 feet above grade, the metering equipment shall be lowered at the Customer’s expense. With approval of a District representative, a permanent meter access platform and steps with a skidfree surface may be installed by the Customer that meets or exceeds the current local Uniform Building Code (UBC). Installation and maintenance will be at the Customer’s expense. After construction, the center of the meter must be between 5 feet and 6 feet above the surface of the platform as shown on Drawing #13.
Section 3.3.9 Platforms for Flood Areas
In flood areas, the bottom of the meter device must be raised a minimum of 3’ above the highest water line on record. If necessary to raise a meter more than 6 feet above grade, a permanent platform and steps with a skid-free surface shall be installed by the Customer that meets or exceeds the current local UBC and maintained at the Customer’s expense. A platform constructed 3 feet or more above grade must have a secure handrail installed on the steps and platform that meets or exceeds the local UBC. After the platform is constructed, the center of the meter must be between 5 feet and 6 feet above the platform surface. A District Representative must be consulted for approval prior to construction. (See Electrical Service Requirements - Drawing # 13)
Section 3.4 Access To Meter Equipment
Section 3.4.1 Meters Not Enclosed
Meters shall not be enclosed or the installation modified in such a way so as to impede safe and convenient access to the meter and associated equipment. Nothing shall hinder or prevent the inspection, removal or installation of meters and other metering equipment, meter rings, meter seals or other locking devices.
Section 3.4.2 Paths to Meters Clear
All pathways providing access to any meter shall be a minimum of 3 feet in width and shall be kept clear of all obstacles and safety hazards, including, but not limited to, landscaping, brush, debris, obstructions, holes, aggressive or dangerous animals, etc.
Section 3.4.3 Walkway Over Open Ditch
Any pathway on the Customer’s property that encounters an open ditch of any type over 2 feet wide shall have a flat, solid, and structurally stable walkway, 2 feet wide with a skid-free surface spanning the entire width of the ditch. All walkways over open ditches must provide a minimum of 1-foot clearance above any water or hazard in the ditch and must not sag more than 1 inch the entire length of the walkway when subjected to a weight of 300 pounds per square foot.
Section 3.4.4 Walkway With Handrail Over Open Ditch
Any walkway on the Customer’s property constructed over an open ditch with a width and depth of 3 feet or more shall have a structurally sound handrail along the entire length of the walkway that will not flex more than 1/2 inches when subjected to a side load of 40 pounds per square foot along the entire length of the handrail.
Working space provisions of the NEC, the current issue, shall be adhered to at the time of installation.
Section 3.5 Security Requirements
Section 3.5.1 Metered and Unmetered Conductors, Same Wireway
Metered and unmetered conductors shall not be installed in the same wireways, pull box, enclosure, etc., except for the conductors being metered from the terminal point to the point of exit at metering enclosures.
Section 3.5.2 Sealing Provisions of Service Equipment
Adequate provisions must be made for the sealing and security of meter, unmetered service equipment, and circuits. Covers and provisions for sealing of all unmetered service equipment, pull boxes, troughs, wireways, busways, etc., shall be provided by the Customer. Unmetered disconnects shall be sealed by the District and accessed only by the District and the Fire Department. Breakers and fuses will not be allowed in unmetered circuits except for flat rate service as specified elsewhere.
Section 3.5.3 Single Sealing Hasp for Covers
All meter base covers shall be equipped with 1 or more securely fastened hasp or stud for padlocking and sealing by the District. Depending on the cover size, nonsealable fasteners may be used to mechanically secure the cover in addition to the single sealing hasp. Covers that secure more than 1 meter shall not be allowed by the District.
Section 3.5.4 Unused Hubs or Openings Closed
Unused hubs or openings shall not be left open. Hubs shall be closed with a blank hub and knockouts with knockout closures, locked in place from the inside. Open, unused breakout, or knockout in meter sockets shall not be allowed.
Section 3.5.5 Watertight Meter Equipment
Raceway or conduit connections at top of meter device shall be watertight and the bottom knockouts closed as detailed in Section 3.5.4.
Section 3.6 Customer Furnished Meter-Mounting Equipment
Section 3.6.1 Socket Forms Allowed
Socket forms allowed or arrangements to provide correct metering for the various systems used in the District are illustrated in Drawing #18
Section 3.6.2 Line-Side Installation of Meter Sockets
Individual meter sockets shall be installed on the line side, ahead of Customer service equipment except as provided for elsewhere
Section 3.6.3 Meters To Be Top Connected
The supply conductors to a self-contained socket shall be connected to the top terminals, and the load supply conductors shall be connected to the bottom terminals. (See Drawings #19, 20, 21, 22, and 23).
Section 3.6.4 Cable Lugs Rated for Conductor
Customer/Contractor shall provide appropriate cable lugs for the termination of District-maintained conductors. When aluminum conductors are used, the meter socket must be listed or approved and clearly marked by the manufacturer that it is acceptable for aluminum conductor.
Section 3.6.5 Oxide Inhibitor Used on Aluminum Conductor
When aluminum service entrance conductors are used in the meter device, the wire should be thoroughly cleaned with a wire brush and then liberally coated with oxide inhibitor.
Section 3.6.6 Meter Base Bonding
The neutral service conductor may be bonded to the meter base using the grounding screw or bonding terminal. The neutral service conductor may be continuous from the weatherhead to the switch box. (See Drawing #20).
Section 3.6.7 Automatic Circuit Closing Devices
Automatic circuit closing devices are not permitted in meter sockets.
Section 3.6.8 Surface Mounting of Meter Sockets
All meter socket equipment shall be surface mounted or flush mounted, not recessed.
Section 3.6.9 Meter Socket Cover Retaining Rings
Meter socket covers may be ringless or ring type. Meter retaining rings shall be screw type. Other types are not acceptable.
Section 3.6.10 Plumb and Rigid Mounting
Meter socket mounting must be plumb and rigidly supported to prevent movement, sway and vibration and able to withstand forces of the installation or removal of the meter. Meter sockets not mounted to a permanent structure must be supported in a manner approved by the District. Refer to Section 3.6.29 and Drawings #14, 15, 16, 17, and 26 for a preferred meter socket support.
Section 3.6.11 Bolt-In Meters
Bolt-in-meter bases, such as the Duncan 400, will not be allowed on any new service
Section 3.6.12 Circular Cast or Drawn Sockets
Circular cast or drawn sockets may be used for temporary services only. (See Drawings #9 and #10 for Temporary Services).
Section 3.6.13 Five-Terminal Sockets Are Required for 120/208
Five-terminal sockets are required for 120/208-volt single-phase services rated up to 200 amperes. The fifth terminal shall be at the nine o’clock position. A #10 AWG wire from the neutral grounded conductor shall be connected to the fifth terminal. (See Drawing #18, socket type “B”).
Section 3.6.14 Box or Trough Sockets
Box or trough sockets may be used in place of circular cast or drawn sockets and are required on 120/208 Volt, three-wire and three-phase services. This type of socket shall be limited to self-contained installations with service entrance conductors that do not exceed #2 AWG copper or #1/0 aluminum and the NEC current rating does not exceed 100 amperes. This type of socket shall also be used for instrument meter services but shall be a minimum of 4 inches deep. The exterior face of the meter base shall not be recessed behind the exterior wall surface.
Section 3.6.15 Seven-Terminal Meter Socket
Up to 200-ampere three-phase services require a self-contained seven-terminal Lever bypass socket unless the source transformer does not serve, nor is intended to serve, other loads. The neutral tap must be connected to the terminal second from the right on the bottom or load side. The socket shall include a grounding electrode bonding clamp. (See Drawing #21).
Section 3.6.16 High Leg Connection
The high voltage-to-ground phase conductor of a four-wire, delta, three-phase service, shall always be connected to the right-hand terminal, top, and bottom. (See Drawing # 21).
Section 3.6.17 Residential Single Phase, 400 Amps or Less
Residential single-phase services rated 400 amperes or less, shall be self-contained metering.
Section 3.6.18 Bypass Meter Bases
Lever and block or shunt type bypasses will be allowed and encouraged for all self-contained meter installations. Automatic bypasses are not allowed. See Section 3.6.7.
Section 3.6.19 Single-Phase Greater Than 400 Amp
Six-terminal sockets with room for test switches are required for single-phase services rated above 400 amperes (2 current transformers located in C.T. enclosure). (See Drawings #25 and 26).
Section 3.6.20 Single-Phase General Power or Industrial Services Greater Than 320 Amps
Single-phase general power or industrial services rated over 320 amperes shall be CT metered.
Section 3.6.21 No Network or Three-Phase Class 320 Locations
Class 320-meter sockets shall not be permitted on any network (120-208 single Phase) or three-phase meter installations. Class 320 single-phase sockets are not permitted on non-residential service of more than 320-amp rating unless approved by the WA State Electrical Inspector
Section 3.6.22 Three Phase Greater Than 200 Amp
Above 200 ampere three-phase requires 1 13-terminal meter base with room for test switch. (See Drawings #27 and 28).
Section 3.6.23 Combined Fuse/Meter Equipment
Where Customer disconnects and/or fuses are combined with the meter equipment, the cover for the meter and the cover for Customer access to the switch/fuse and load side wiring shall be separated such that District meter and line-side service compartments may be secured and sealed separately from Customer side. On such combination units, internal barriers shall be permanently installed to prevent access to meters and unmetered wiring via Customer compartments. On multi-meter equipment, the line-side cable terminal compartments shall have sealable and lockable covers separate from meter covers.
Section 3.6.25 Ground Rod Required
Every pedestal-mounted meter shall have at least 1 ground rod at the meter location with a minimum #6 copper ground wire connecting the ground rod(s) to the meter base. 2 ground rods are required at the service panel location. (See Drawings #14, 15, 16, and 17).
Section 3.6.26 Meter Pedestal on Same Lot as Customer Served
When a remote meter pedestal is utilized, it shall be located on the same lot as the Customer being served.
Section 3.6.27 Parking Area Protection
When a meter pedestal is located in a parking area, it must be so located that parked vehicles will not restrict meter accessibility nor meter pedestal be damaged by vehicular traffic.
Section 3.6.28 Transformer-Meter Pedestal Clearance
The meter pedestal shall not be closer than 5 feet to the side or 10 feet from the front of a padmount transformer without prior approval of the District. (See Drawings #14, 15, 16, and 17).
Section 3.6.29 Meter Pedestal Support
- An assembled meter pedestal, which is composed of a meter socket and conduit or raceways, must be secured in a minimum 36 inches x 36 inches x 4 inches concrete slab. (See Drawings #14, 16, and 17) and supported by any 1 of the following:
- A single 1 inch x 4 inches galvanized steel channel
- Two pieces of heavy-duty, 1-5/8 inches x 1-5/8 inches galvanized, uni-strut.
- Two pieces of 2-inch galvanized rigid conduit.
- Two pieces of 2-inch x 2-inch galvanized angle iron.
- A one-piece, metal sleeve mobile home base assembly must be set a minimum of 2 feet in the ground and secured in a minimum 36 inches x 36 inches x 4 inches concrete slab (see Drawing #15).
The customer is responsible for maintaining the pedestal in plumb (vertical) position and to fulfill all other maintenance requirements. (See Section 3.6. 32)
Section 3.6.30 C.T. Pedestal Support
- An assembled C.T. pedestal, which is composed of a C.T. can, meter socket, and conduit or raceways, must be secured in a minimum 48 inches x 36 inches x 4 inches concrete slab. (See Drawing #26) and supported by any one of the following:
- Two pieces of heavy duty, 1-5/8 inches x 1-5/8 inches back to back, galvanized unistrut.
- Two pieces of 2’ galvanized rigid conduit.
The Customer is responsible for maintaining the C.T. pedestal in plumb (vertical) position and to fulfill all other maintenance requirements. (See Section 3.6.32)
Section 3.6.31 Meter Socket Maintenance by Customers
It is the responsibility of Customer/Building Owner to maintain, repair, and replace the meter mounting (socket) equipment in order to keep such equipment in a safe, secure, and useable condition. This shall include any and all maintenance that is discovered by the District during authorized activities including, but not limited to, meter testing, meter maintenance, meter change-out, meter disconnect or connect. When such equipment is subject to vandalism or damage, it is the responsibility of Customer/Building Owner to remedy the situation by protective measures or by changing meter location.
Section 3.6.32 the District Will Perform Emergency Repair
The District will perform emergency repair in an attempt to maintain or restore service and to protect the public safety. In the event that the hazard posed by the equipment is critical to safe operation, immediate disconnection of service may be necessary until corrections are made by the Customer/Building Owner. The District will notify Customer/Building Owner and the Inspection Authority when an unsafe meter socket and/or service equipment problem is found. The District will allow a reasonable time, normally not to exceed 30 days, for the repair or replacement of meter socket equipment, subject to the hazard involved. The District emphasizes the need for the responsible Building Owner to minimize safety hazards to all concerned by maintaining meter socket equipment and service compartments in a safe and good working order.
Current transformers (C.T.s) shall be furnished, installed, and owned by the District. Contractor installed 1 inch diameter rigid galvanized or 1 inch SCD 40 rigid PVC conduit shall extend from the meter base to the approved instrument transformer enclosure located at a distance not to exceed 50 feet. For distances greater than 50 feet, contact the District. No conduit outlet bodies or other non-sealable fixture shall be allowed between the C.T. enclosure and meter base. Metering connectionsshall be made by the District. The Contractor shall identify and tag all conductors indicating common phase and whether they are source and load.
Section 4.1 Ampacity up to 800 Amps
Section 4.1.1 General
District C.T.s shall be mounted in Customer provided, owned, installed and maintained enclosure, compartment, box, or as part of panel boards as specified herein. The C.T. enclosure, compartment, box, etc., is dedicated for metering purposes only. Unauthorized access is not permitted. No Customer equipment or other wiring shall be allowed in or to pass through the dedicated space. C.T.s shall normally be installed on the source-side of the service disconnect - unless otherwise authorized by variance process.
Section 4.1.2 Outdoor Installation
All C.T. installations rated at 800 amps or less shall be mounted outdoors and shall be installed in weather tight approved cabinets, except C.T.'s mounted on poles(See Section 4.1.11). In some areas the exposed portions of CT enclosures must be fabricated using 300 series stainless steel. Contact a District representative for any service location within ½ mile of a coastline.
Section 4.1.3 C.T. Enclosure and Conduit by Customer
Customer provides the C.T. enclosure with landing pads rated for the service ampacity, installs line and load-side wiring, and provides necessary “meter conduit.” The Customer shall terminate all service conductors to the current transformer landing pad. All connectors shall be bolted to the landing pads with stainless steel bolts, flat washers, Belleville washers and silicone bronze nuts or installed into lugsthat are provided with the C.T. enclosure as per detail on Drawing #33. The high leg conductor of a delta service shall be marked with orange tape and connected on the right-hand side in the C.T. enclosure. The Contractor shall identify and tag all conductors indicating common phase and whether they are source or load.
Section 4.1.4 District Instrument Transformers
The District provides and installs bar-type C.T.s. The District attaches the C.T.s to the landing pads mounted to the back of the current transformer enclosure and installs the metering conductors and test switches and installs the meter.
Section 4.1.5 the C.T. Enclosure Sizes Required
The C.T. enclosure sizes required shall be as listed below:
| Service Size | Minimum Enclosure size (Height x Width x Depth) |
|---|---|
| 400 Amperes Single Phase | 36 inches x 36 inches x 11 inches with Hinged Door |
| 600 Amperes Single Phase | 36 inches x 36 inches x 11 inches with Hinged Door |
| 800 Amperes Single Phase | 36 inches x 36 inches x 11 inches with Hinged Door |
| 400 Amperes Three-Phase | 36 inches x 36 inches x 11 inches with Hinged Door |
| 600 Amperes Three-Phase | 48 inches x 36 inches x 11 inches with Hinged Door |
| 800 Amperes Three-Phase | 48 inches x 36 inches x 11 inches with Hinged Door |
In some instances, larger enclosures may be required to accommodate conductor bending radius requirements.
Section 4.1.6 Cabinet Cover Size
Cabinet covers, pull box covers, C.T. cabinet covers, and any miscellaneous service equipment covers shall be limited to 36 inches by 48 inches. All covers shall be hinged. All doors shall be equipped with provisions for locking.
Section 4.1.7 Cabinet Mounting Height
Current transformer enclosures shall be mounted such that the bottom of the enclosure is no higher than 3 feet above grade or the bottom lower than 6 inches above grade. (See Drawing #26).
Section 4.1.8 No Meters on C.T. Enclosure Cover
The cover of an instrument transformer enclosure shall be free of meters or equipment.
Section 4.1.9 C.T. Enclosure Not a Conductor
The current transformer enclosure shall not be used as a current carrying conductor.
Section 4.1.10 Enclosures Shall Be Grounded
All outdoor current transformer enclosures shall be grounded with a #6 copper ground wire to a ground rod at the meter location. (See Drawings #25, 26, 27, and 28).
Section 4.1.11 C.TS Mounted on Service Poles
C.T.s may be mounted on service poles when the Customer wiring extends directly from the service pole to multiple load centers. The District shall supply a suitable mounting bracket for the C.T. (See Drawing #8).
Section 4.1.12 Mast-Mounted Current Transformers Shall Not Be Allowed
Section 4.1.13 Outdoor Installation Locations
The meter device shall normally be mounted on an outdoor building wall, a remote pedestal, or a service pole. The meter enclosure or socket, subject to meter location policy, should be located as close as practical to the C.T.s. Enclosures shall not be located in carports, breezeways, porches, or such locations where subsequent addition, rewiring, or remodeling could enclose the enclosure. An enclosure installed in an alley or driveway must be recessed in the wall or protected adequately to prevent damage from vehicular traffic.
Section 4.1.14 Metering Not on District Equipment
Metering, except current transformers, shall not be mounted on or in District equipment except on service poles if approved in advance. All pole-mounted meter equipment shall be grounded with a #6 copper ground wire to a ground at the meter location. (See Drawings #7 and 8).
Section 4.2 Service Ampacity Larger Than 800 Amperes
Section 4.2.1 Switchgear C.T.
For services with ampacity greater than 800 A, the C.T. enclosures shall be part of the Customer service panels or switchgear. The District should be consulted for review of compartment size and service prior to purchasing and installing equipment. The C.T. space shall have bus bars through the C.T.s that are removable from within the C.T. compartment space. The C.T.s shall be furnished and installed by the District. Cables must be landed on hardware independently supported from the bus link through C.T. window. Cables shall not be brought through the C.T. window. Customer or Contractor shall terminate all conductors with 2-hole connectors and bolt to the current transformer landing pad bus bars. (See Drawing #29A and 29B).
Section 4.2.2 Enclosures To Be Accessible
Enclosures shall not be installed on ceilings. If the enclosure is installed on a balcony or platform, it must be available by a permanent stairway and be surrounded by a railing, both of which conform to OSHA requirement.
Section 4.2.3 C.TS Readily Accessible
On switchboards, the instrument transformers shall be installed in such a manner as to be readily accessible after all bussing is in place. Installation plans regarding size of cubicle and placement of equipment shall be approved by the District before switchboard manufacturing. Neutral connections for metering shall be readily accessible and sealable. If CT’s are in enclosed area including, buildings, fenced areas etc. The customer shall be responsible for purchasing a lock box labeled for the District use only. The lock box will contain a key for entry to enclosed area. The District must pre-approve any substitutions for the lock box.
Section 4.2.4 Unmetered Conductor Compartments Sealed
All sections of the switchgear that contain unmetered conductors shall have provisions for sealing compartment doors or covers.
Section 4.2.5 Meter Base & Test Switches
Meter base and bypass switches cannot be integral to switchgear equipment. Preference is for mounting on side of CT cabinet (See Drawing 29B). The district provides meter CT wiring and test switches. Contractor provides and installs meter base, and conduit
Section 4.3 Primary Voltage Meter Installations – Over 600 V
Section 4.3.1 Metering Location Approval
Primary service is metered with the instrument transformer(s) located outdoors and will be either pole-mounted or pad-mounted. The location of all instrument transformer metering installations must be approved by the District in advance of any work by the Customer or Customer’s contractor. The primary metering shall be located at the interface between District facilities and the Customer's facilities.
Section 4.3.2 District Provides, Installs, Maintains, & Owns Metering and Associated Equipment
At customer expense, the District will provide, install, maintain, and own all equipment associated with primary metering up to the load side of the current transformer(s) on all pole or pad-mounted installations
Section 4.3.3 Customer Provides Switches, etc.
Customer provides all necessary– primary wiring, switches, fusing or other overcurrent protection, lightning arresters, grounding and etc., from the load side of the current transformer to the Customer’s service equipment.
Section 4.3.4 Customer’s Wiring Connected by District
The District will connect Customer’s wiring to District primary voltage supply conductors and instrument transformers.
Section 4.3.5 Pole Mounted Primary Metering
Pole mounted primary metering will be mounted on a District owned pole.
Section 4.3.6 Pad Mounted Metering Enclosure
At Customer expense, the District will provide, install, own and maintain padmounted metering enclosures for underground installations.
Section 5.1 Notify District of New or Rewire Work
Customer or Contractor should promptly notify the District (refer to Section 1) of the electrical work planned. Prompt notification will minimize wiring problems and avoid unwanted delays when work is completed.
Section 5.2 Wiring Inspection
Customer wiring may be subject to inspection and approval by Washington State Wiring Inspector. Contact Department of Labor and Industries for requirements. For areas outside of L&I jurisdiction a property owner representative must authorize, in writing, the energizing of service wiring in conjunction with an independent electric inspection. Circumstances generally requiring wiring approval before service can be connected or reconnected are:
- New wiring is installed or existing wiring is added to, repaired, or altered.
- Any service de-energized for more than one year.
- Fire - Service has been ordered disconnected by the Fire Department, disconnected by the Fire Department themselves, or disconnected by the District personnel because of hazard to the public.
- Storm or Vandal Damage - Disconnected by the District personnel because of danger or hazard to the public. The District will promptly notify the inspection authority.
- Ordered disconnected by an electrical inspection authority because of defective or hazardous wiring.
- Disconnected by District personnel upon observing a hazard to the public caused by Customer wiring. The District will promptly notify the electrical inspection authority.
- Disconnected by District personnel at the request of the Customer or their electrical Contractor in order to add to, repair, or change the wiring. (Contractor can usually arrange by telephone for the electrical inspection authority to give verbal wiring approval to the District).
Section 5.3 Emergency Repairs After Hours, Weekends, & Holidays
Reconnection can be made for emergency reasons if Contractor provides the District with electrical license and work permit number. The District will promptly notify electrical inspection authority of this action.
Section 5.4 Diversion of Service
It is illegal to tamper with a District meter or metering equipment and to make unauthorized connections and reconnections of service with the intent to divert electrical energy from being properly metered. Such diversion is subject to service cutoff and legal action.
Section 5.5 Contractor Access
Contractor may access Customer-owned and District secured meter and C.T. equipment in the pursuit of legitimate work. The Contractor is required to inform the District within 24 hours of this action and the work intended, by calling the appropriate District office. Failure to provide prompt notification will cause access to be considered unauthorized and subject to legal action.
Section 5.6 Grounded Neutral
All services shall have a grounded neutral. Three-phase, three-wire metered services are not permitted.
Section 5.7 Communication Bonding
Telephone and/or other electronic equipment may require grounding external to Customer premises. Such ground connections are not permitted inside District sealed and secured cable and meter compartments.
Section 5.8 Distribution Center Pole Metering
Farm Customer may desire service at a number of locations making it uneconomical to distribute from a meter located at the residence. In such cases, Customer can request a distribution center pole on which District meter is installed and from which Customer extends service to the various locations.
Section 5.9 Transfer Equipment
Transfer equipment, including transfer switches, shall operate such that all ungrounded conductors of District source of supply are disconnected before any ungrounded conductors of the second source are connected.
Section 5.10 Customer Generation
The following general requirements apply to customer generation facilities designed to operate directly connected to the District’s electrical system (parallel operation) and those that are designed to operate isolated from the District’s system (non-parallel operation). Requirements and specifications for various types and sizes of customer facilities shall be obtained from the Customer Service Representative prior to installation.
- Standby Generation (Non-Parallel Operation)
The Customer may install a standby generator to supply all or part of the load in the event of a service interruption. The customer’s wiring shall be arranged so as to prohibit the interconnection of the District’s service and the customer’s alternate source of supply. This will require the installation of a double-throw switch or its equivalent as approved by the District. Drawing #37 schematically illustrates some typical installations of standby generating equipment.Note: Precautions must be taken where alternate means of generation are employed, whether emergency or otherwise, to eliminate the possibility of electrical connection between the District’s service and the customer’s alternate source of supply. The customer must notify the District and provide electrical details of generator installation and isolation from the District’s system. - Auxiliary Generation, Net Metering and Production Metering (Parallel Operation)
Prior to the installation and operation of any auxiliary generation facilities (e.g. wind turbine, solar panel, etc.) and net-metering or production metering, the customer must notify the District to obtain approval for the installation and enter into an Interconnection Agreement for metering. Additional information and requirements can be found in District’s Net Metering Reference Materials:- Customer Checklist for Utility Interconnection
- Standards for Interconnection with Electric Generators
- Application for Interconnecting a Generating Facility No Larger than 100KW
- Net Energy Metering Interconnection Agreement
- Generating Facility Certificate of Completion
- Cogeneration (Parallel Operation)
Co-generators are defined as facilities that produce electrical energy and utilize the heat energy by-product for other purposes (e.g., heating or cooling). The customer must notify the District prior to the installation of this equipment in order to provide design information and obtain approval for connection of the equipment the District’s facilities
Section 6.1 General
Customer is advised to consult the District before purchase, installation, or wiring of motors or other apparatus to determine the kind of service that will be supplied and the manner in which such equipment should be connected.
Section 6.2 Motor Characteristics
All motors, apparatus, and appliances shall have such characteristics, which enable the District to maintain a satisfactory standard of service to Customer being served and all other Customers in the immediate area, including starting current and harmonic characteristics. Customers shall install no motors whose starting shall cause a voltage drop greater than 3% at the service meter point where such service supplies non-motor loads, nor greater than 2% at a neighboring point of service. Changes in District service equipment to accommodate such motors may be at Customer expense.
Section 6.3 Service Type Designation by District
The District reserves the right to select the type of service to be supplied and should be consulted before equipment is purchased or ordered. Single phase motorslarger than 5 horsepower or a combination of single or poly-phase motors exceeding 15 horsepower requires approval of the District.
Section 6.4 Special Motors
Starting current mitigation or soft start technology at customer expense may be a requisite to meet Section 6.2 requirements, including application three-phase motors beyond single-phase conversion devices. Starting motors across line voltage is permitted where Section 6.2 requirements are maintained.
Section 7.1 Under-Voltage Protection
All motors and special apparatus should be equipped with suitable undervoltage time delay tripping devices to protect against sustained undervoltage or service interruption and to prevent automatic disconnection of equipment upon momentary voltage disturbance.
Section 7.2 Single-Phase Protection
Three-phase motors should be equipped with suitable protective devices to prevent single-phase operation, improper direction of rotation and excessive heating due to over current.
Section 7.3 The District Will Not Be Responsible for Damage
The District will not be responsible for damage to Customer equipment due to failure of Customer to provide adequate protection.
Section 7.4 Uninterruptible Power Supply
Customer should consider installing an Uninterruptible Power Source (UPS) or voltage suppressers where momentary or extended outages or voltage fluctuations will cause inconvenience, loss of electronic memory, or trip alarms, etc.
Section 8.1 General Cable Trench Requirements
- Customer Provided
All trenches shall be provided by the Customer. Inspection and acceptance by the utility’s representative is required - Definition
Trench shall be defined to mean trenching, bedding, backfilling, restoration, and maintenance of subsequent ditch settling for electrical cables and conduits. - Notification
The District, all participating utilities, and the Underground Locating Center, shall be notified a minimum of 48 hours in advance of the date and time for the right-of-way trenching and facility placement. Locating services notification is required by state law.
Section 8.2 Root & Rock Restrictions
The trench shall be free of rocks or roots greater than 2 inches in diameter
Section 8.3 Specification Drawings
The trench shall be dug to the specifications shown on Drawings #30, 31, and 32, unless otherwise approved by a District representative.
Section 8.4 Water-Free Trench
The Customer is responsible for installing well points, pumping, or other measures to provide reasonably water-free trenches.
Section 8.5 Access, Construction
To facilitate installation, the Customer shall place all excavated material in a manner, which allows the District’s installation vehicle to drive on the opposite side of the trench the full length of the project unless other specific arrangements are approved by the District representative.
Section 8.6 Sloping and Shoring
Any area where District personnel must enter the trench shall be excavated in accordance with Chapter 296-155 WAC of the Washington State Safety Code. The Code requires that the excavated material be at least 2 feet from the edge of the trench and that any trench over 4 feet deep be sloped, shored, sheeted, or otherwise adequately protected.
Section 8.7 Joint Use of Trenches (See Drawing #30)
Section 8.7.1 Direct Buried Cable Separation
A minimum vertical and horizontal separation of one foot must be maintained between direct buried electric cables and communication cables.
Section 8.7.2 Electric Cable in Conduit, No Separation Required
Electric cables installed in conduit and communication cables may be buried together at the same depth with no deliberate separation between facilities if both utility owners concur.
Section 8.7.3 Water and Sewer Lines
A water service line, up to 1½ inches may be installed at 18 inches above District cables. No sewer lines or water mains will be allowed in any electrical trench.
Section 8.8 Permanent Access
All surface areas above direct-buried cable and cable in conduit must be accessible for future District operations including, but not limited to, maintenance, location, repair, and replacement. The Customer shall not construct any building, fence, landscaping device, or other obstruction over the direct-buried cable route that restricts said access. In addition, customers should consider that cable in conduit routes may also need to be accessed in the event the conduit system fails or otherwise needs to be repaired or maintained. All transformers and other aboveground devices must remain accessible to District vehicles at all times and the opening side of the device must have at least 10 feet of clearance from any obstruction. The District handout on padmounted equipment requirements provides more details. (See Drawings #34 and 35). Failure by the customer to maintain accessibility to all District facilities may result in delays in repairs and the restoration of service to the customer.
Section 8.9. Cable Pulled Into Continuous Conduit
When service cable is installed in continuous conduit, the cable shall be pulled into conduit after it has been assembled (conduit shall not be installed by slipping over cable as it introduces rock and dirt into the conduit and does not allow for an adequate sealing procedure). See Chart #1 for minimum conduit and sweep sizes allowed for conductor sizes.
Section 8.9.1 PVC Joints Must Be Glued
Each PVC conduit joint must be permanently glued, prior to cable installation.
Section 8.9.2 Maximum Number of Bends in Service Conduit
Total number of bends in a service run shall not exceed 360 degrees. All bends shall be long radius type (24-inch minimum). See Chart #1 for minimum sweep dimensions for various conduit sizes.
Section 8.9.3 Conduit Under Buildings
No structure may be built over District facilities except when it is absolutely unavoidable. Written approval of the Manager of the District is required.
- The required conduit(s)shall be paralleled by an equal spare conduit(s) from the pole to the vault or between vaults
- Conduits shall not pass through nor conflict with the building’s foundation walls.
- Conduit(s) shall be encased in concrete. Minimum encasement shall be 2 inches thick on all sides of the conduit.
- Exception: The concrete encasement requirement can be waived if the building will have a minimum 4-inch thick concrete slab first floor and no basement.
- A Hold Harmless Clause will become part of the power line easement.
- Total number of bends shall not exceed 180 degrees.
- Continuation and restoration of service cannot be assured if a structure is built over District lines. 1 of the following remedies shall apply:
- Removal of the structure(s).
- Payment to reroute the line(s) around the structure(s).
- Customer acknowledgement that additional restoration expense caused by the structure(s) shall be billed to the customer. This will generally apply when a cable fault occurs under the structure and the raceway, if available, is unusable.
Section 8.10 Equipment Locations Permanent
The Customer is responsible for establishing the location and grade of the cable trench route and transformers, junction boxes, or secondary pedestals that are shown on the sketches provided by the District. The transformer, junction box, and pedestal locations are considered permanent and moving them is difficult and expensive. In the event any of these facilities need to be relocated, the entire cost will be at the Customer’s expense. We recommend that a licensed surveyor be used to determine the lot lines, property corners, right-of-way, and easements to ensure that the facilities are properly located
Section 8.11 the Customer Shall Provide Final Grade
The Customer shall provide final grade at the site of a transformer or other aboveground devices. After installation, the Customer shall not change the cable depth by cutting or filling without the express consent of the District.
Section 8.12 Backfill Bedding Material
Bedding material for backfill will be subject to approval by a District representative. The Customer will provide the appropriate bedding material when native material is unsuitable. The Customer shall place the approved bedding material in the trench in sufficient quantity to protect the conduit, prior to installation. The Customer shall place an equal amount of approved bedding material over the installed conduit prior to backfilling with native materials. The typical requirement is 6 inches of bedding below and 6 inches above the conduit.
Section 8.13 Backfill Compaction
All trenches shall be compacted to the satisfaction of the District in the following manner:
- Compacted sufficiently to prevent later settling of the fill material.
- For Trenches compact in lifts to attain 95% compaction. The Customer shall provide compatible 1 inch minus granular material (i.e. sand, screen reject, or pit run) should the District determine that native material is unsuitable for backfill. The surface material shall be replaced with material equal to existing surface (crushed rock, asphalt, concrete, etc.).
- For beneath transformers, pedestals, and above-grade devices - Compact in lifts to attain 95% compaction. The Customer shall provide compatible 5/8 inch to 3/4 inch minus granular material.
Section 8.14 Road Bores
All road bores should begin at a depth of 42 inches to the bottom of the bore hole and exit or end with a depth of no less than 36 inches or no more than 48 inches below grade. Lesser or greater depth will not be accepted without the approval of a District representative. In addition, a gradual transition from the end of the bore into the 42 inch trench or excavation must be provided by the contractor
Section 8.15 Requirements Before Construction
The District will schedule the Customer’s project only after required easements are received and necessary monies are paid. Trenching should not be started before consultation with a District representative and a date scheduled for the work. At this consultation, any special requirements for the trench will be outlined. The trench shall then be dug prior to the arrival of a District crew on the scheduled date.
Section 9.1 General
District will install area lighting facilities on District poles. New light installations are to conform to the specifications listed below and in accordance with WAC296 46B. Existing contracts may be supplemented with additional lights utilizing previous installation methods as subject to NESC and NEC code restrictions
Section 9.2 Maintenance by District
District-owned light fixtures and services are maintained by District.
Section 9.3 Rates
Rates are based upon the light output and installation requirements. Contract rates apply with municipal Customers; flat rates apply for individual Customers as per District Rate Schedules.
Section 9.4 Served From Overhead Systems
Section 9.4.1 District Lights on District Poles
District-owned and installed lights are installed on District owned and installed poles. If a new pole and/or transformer is required for service, special installation and monthly rates will apply. The following procedures apply:
- Service contract signed by Customer.
- Installation charges paid by Customer.
- District installs pole, light, runs service, and maintains facilities.
Section 9.5 Served From Underground System
Section 9.5.1 District Lights on District Poles
District owned and installed lights are installed on District owned and installed poles. If a new transformer is required to provide service, an installation and special monthly rate will apply. The following procedures apply:
- Service contract signed by Customer.
- Installation charges paid by Customer.
- Trench and backfill by Customer from source to light pole, if required.
- Cable (minimum #12/2 cu, per NEC) and conduit, installed by customer from transformer or secondary pedestal to pole.
- District installs light, connects service cable and maintains facilities
Section 9.5.2 Multiple Lights
Multiple lights running off a single service run shall be metered, customer installed and maintained.
Section 10.1 Contact Approval Required
Contact approval is required for foreign contacts on District poles. Approval requires prior request to install and field check by District representative to determine that adequate space is available.
Section 10.2 District Riser Requirements
District Riser requirements regarding standoff brackets apply. A minimum of 6 inches of space between the cabinet and the surface of the pole to which it is mounted shall be maintained
Section 10.3 Washington State Wiring Permit Required
Wiring permit requirements apply. The equipment wiring shall be inspected by the Washington State Wiring inspector and approved prior to electrical connection by the District.
Section 10.4 Dimension and Weight Limits
Maximum size shall be 26 inches wide x 36 inches high x 16 inches deep and weigh 500 pounds or less.
Section 10.5 Equipment Grounding As per NEC
The equipment shall be effectively grounded to a grounding system installed by the communications company. Ground rod(s) shall be installed a minimum of 18 inches from the base of the pole on which the equipment is mounted.
Section 10.6 Clearances As per NESC
The schedule 40 PVC or galvanized metallic conduit, capped with a weatherhead, shall terminate 8 inches below the level of the District’s overhead secondary attachment or neutral position. The service shall include 18" of tail at the weatherhead. The Cabinet shall be mounted with the bottom no lower than 12 feet above ground.
Section 10.7 Voltage and Protection
The unit shall be designed to operate from connection to a 240/120-volt, single-phase District secondary and will include back-feed voltage protection to prevent power from the unit being routed into the District’s system.
Section 10.8 Battery Flame Protection
Battery pack auxiliary power supplies shall have batteries in the assembly, which have flame arrester vent caps and shall be protected from electrical spark by having separate metal containers. The batteries shall be located above the assembly’s power inputs and transformer units to insure isolation of any gasses from open flame or spark. The battery containers and the cabinet shall be well vented
Section 10.9 Load Information Required (Wattage of Power Supply)
The District shall be notified of the connected load of the power supply prior to connection
Section 10.10 Rates
In addition to the standard attachment fee, the customer shall pay the District a flat rate to cover the cost of providing electrical service to the auxiliary power supply unit. This rate shall be based upon the connected load.
Section 10.11 Transfer and Relocation
In the event that it is necessary to replace or relocate a pole on which an auxiliary power supply unit is mounted, the customer shall transfer or relocate the unit at no cost to the District
Chart # 1 Non-Metallic PVC Direct-Buried Conduit
PVC Conduit must meet the following requirements:
- The following information shall be imprinted on all PVC conduit:
- Manufacturers name or trademark
- Nominal size
- Material (PVC)
- Schedule 40 or 80 PVC is required for service riser according to the NEC and NEMA STANDARD for applications listed below:
- Type III - Designed for normal-duty applications above ground (Sch 40).
- Type IV - Designed for heavy-duty applications above ground (Sch 80) (Hazardous areas, e.g. next to driveways).
- Conduit bends shall be long-radius type
i. Minimums:
2 inches to 24 inches Radius
3 inches to 30 inches Radius
4 inches to 48 inches Radius
6 inches to 60 inches Radius
- Residential secondary service conduit shall be a minimum of 2 inch Schedule 40 PVC, NEMA Standard TC-2.
- 5 inch conduit is not a District standard; must use 6 inch to be compatible when the District will be extending customer/contractor-installed conduits.
Chart # 2 Minimum Conduit Size Based on Maximum Fill Requirements, Triplexed and Quadruplexed Secondary Conductors
| XLP Conductor | Triplex | Quadruplex | |||||
|---|---|---|---|---|---|---|---|
| Size | Nominal | One | Two | Nominal | One | Two | |
| Phase | Neutral | O.D. | Run | Runs | O.D. | Run | Runs |
| 1/0 | 2 | 1.06 inches | 2 inches | 3 inches | 1.42 inches | 3 inches | 3 inches |
| 2/0 | 1 | 1.17 inches | 2 inches | 3 inches | 1.59 inches | 3 inches | 4 inches |
| 3/0 | 1/0 | 1.27 inches | 2 inches | 3 inches | 1.72 inches | 3 inches | 4 inches |
| 4/0 | 2/0 | 1.39 inches | 2 inches | 3 inches | 1.88 inches | 3 inches | 4 inches |
| 250 | 3/0 | 1.53 inches | 3 inches | 4 inches | 2.08 inches | 3 inches | 4 inches |
| 350 | 4/0 | 1.72 inches | 3 inches | 4 inches | 2.34 inches | 3 inches | 6 inches |
| 500 (300) | 2.00 inches | 4 inches | 6 inches | 2.71 inches | 4 inches | 6 inches | |
| 750 (400) | 2.35 inches | 4 inches | 6 inches | 3.22 inches | 4 inches | 6 inches | |
| 1000 (500) | 2.66 inches | 4 inches | 6 inches | 3.63 inches | 4 inches | n/a | |
(400) and (500) minimum size for neutral ampacity.
(300) size per Essex Cable Handbook could be 250 and have required neutral ampacity.
5-inch conduit is not District standard; must use 6 inches to be compatible when the District will be extending customer conduits.
Use NEC conduit sizing where the District will not own the conductors.
Chart # 3 Conductor Sizes and Types Allowed for District Service Wiring Installations
Residential Service Conductors
Aluminum Only
2
1
1/0
2/0
3/0
4/0
250
350
500
See Charts 1 & 2 For District Conduit Requirements
General Power and Industrial
Copper or Aluminum
Per NEC
Drawings contained here illustrate items of text and some typical service and meter arrangements. Further detail on these and other types of service arrangements may be obtained from the District. All installations must comply with the current NEC at the time of installation, and local ordinances or other requirements.
- Service Brackets
- Overhead Strike to Residence
- Guying - Stiff Leg Type
- Clearances: Services Over Ground and Roofs -A
- Clearances: Services Over Ground and Roofs -B
- Service Assembly Underground from Overhead Take-off
- Metering Assembly, Self Contained, Pole Installation
- Metering Assembly, CT, Pole Installation
- Service Assembly, Overhead Temporary
- Service Assembly, Underground Temporary
- Metering Assembly, Wall Mounted, Self Contained
- Meter Location On Buildings
- Platforms For Elevated Meters
- Meter Pedestal, Self-Contained
- Meter Pedestal, Mobile Home
- Meter Pedestal, 320 Amp Service
- Meter Pedestal, CT Meter
- Meter Socket Clip Arrangement
- Meter Socket, 200 Amp, Single Phase
- Metering, Self-Contained, Overhead Service, Single Phase
- Metering, Self-Contained, Overhead Service, Three Phase
- 320 A Lever Type Bypass Meter Base (Underground)
- 320 A Lever Type Bypass Meter Base (Overhead)
- 208/120V 3-Phase 4-Wire to Serve Multiple Occupancy
- CT Enclosure Wiring, Single Phase, 400 to 800 A, Overhead
- CT Enclosure Wiring, Single Phase, 400 to 800 A, Underground
- CT Enclosure Wiring, Three-Phase, 400 to 800 A, Overhead
- Metering, Overhead Service, Three-Phase, C.T. 400 to 800 A
- Metering, Underground Service, Three-Phase, C.T., 800 A or greater
- Trench Requirements - Depth, Width, Clearances
- Underground Service, Wall Mounted Meter
- Underground Service, Meter Pedestal
- Conductors Terminated in Padmount Transformers by Customers
- Padmount Transformer Clearances
- Guard Posts for Padmount Transformers
- Intentionally Blank
- Standby Generator Schematic Connection Diagrams
- Electric Service Regulations (PDF)
- Electric Service Requirements (PDF)
- Electric Service Requirement Diagrams (PDF) – Diagrams for electric service requirements.